FoamCoat. We're not just a roofing company
Puddling water after rain evaporates without penetrating the sealant layer.















MARYLAND TRANSIT AUTHORITY

PROJECT

The MTA’s roof had extremely high energy costs and a badly leaking roof. Their study of choices to solve their problems led them to a foam roof with extra-durable coating. Gravel was removed from the existing roof and three inches of VFI polyurethane applied over the entire roof surface. Expansion joints received a fourth inch. A total of 70 mils of polyurea base coat and top coat were then applied over the foam. Around mechanical units and projections an additional 50 mils was added.

CHALLENGES

Time was a major challenge as the project had to be completed within 45 days. Track side training was required for all personnel prior to their work due to the hazards of the rail service. Limited set-up/work areas meant materials were stored off-site and delivered to the site daily. The MTA is a three-shift operation, so FoamCoat had to work quickly, with minimal disruption.

SYSTEM DESCRIPTION

  • 1007 and # 11 primers for various surfaces, 215 urethane coating, 730 Polyurethane foam, 277 Polyurea 540R base coat, 277 Polyurea (aliphatic) top coat
RESULT

The leaking has been stopped. The roof has been made considerably more durable (another objective of the Authority). The R-value has been increased from roughly seven to roughly 28 total R-value. MTA estimates that they will recover total energy costs for this project within 5 years and every year after that will be a positive return on their original investment. [I’d call that an impressive stewardship of funds with a better-than-usual ROI.)


Back